Stage One: Clearing and levelling the area (3m x 1.5m), setting the post supports and building the framework and roof. We used the same post-setting method that was used for the shelter posts, and for the framework we used some spare Opepe wood. As we had done on the shelter, we waterproofed the woodshed using butyl rubber lining. We built the roof using the leftover timber and asphalt roof tiles from the shelter, and fixed some temporary wall planks.
|
||