2022 Furnace ('Phoenix') and Lehr at Quarley - Phoenix Firing Five (May 2022)

Projects: 2019 Onwards   Wood Gathering and Processing   Phoenix Firing Three   Repairs after Firing Three   Phoenix Firing Four

Phoenix Firing Five   The New Shelter Floor   The Electric Kiln   Rebuilding the Lehr   Etna Build and Firings   General Photos

Vesuvius Firepit Build   Vesuvius Superstructure Build   Vesuvius Firings   Repairs after Firing Five   Phoenix Firing Six



Furnace Performance and Lehr



Pots and Breakages



Glassblowing

(Photo
There was no need to repair the furnace after Firing Four, so we could proceed directly to Firing Five.

This was a five-day firing, running from the 18th to the 22nd May, 2022, two days after Firing Four, and was devoted to glassblowing.

We lit the furnace at around 07.30 and charged the pots at about 09.30, when the furnace temperature reached 1000°C. We blew glass from about 10.00 until 13.00, broke for lunch, worked from 14.00 until about 19.30 (but with a tea break!), usually finishing at 20.00, after emptying the pots. This meant that total blowing time each day was about ten and one half hours hours (except on the final day, when we stopped blowing at 17.30, and finished at 18.00).